Two figures are routinely confused at renewal. Market value is what a buyer would pay for the asset as it stands, including the land it sits on. Reinstatement cost is what it would cost to rebuild or replace it new, excluding land, and including everything a rebuild actually consumes. Insurers price and settle on the second.
Why market value is the wrong number
A villa in a prime community may have a market value well above its rebuild cost, because the land carries much of the price. A specialised industrial facility may be the reverse: expensive to build, difficult to sell. Insure either on market value and the cover is wrong — the first wastes premium, the second leaves a gap that only appears at claim time.
What reinstatement cost includes
- Construction cost of a modern equivalent to current standards and current regulations
- Demolition, site clearance and making safe after the loss
- Professional fees — design, engineering, supervision, permits and approvals
- Inflation over the policy period and over the rebuild programme
- Escalation for constrained supply, imported materials and specialist trades
- Where relevant, loss of rent or alternative accommodation over a realistic rebuild period
Underinsurance and the effect of average
Where a policy contains an average (or under-insurance) condition and the sum insured is below the true reinstatement cost, the insurer may reduce settlement proportionately — including on partial losses. A property insured for 70% of its reinstatement cost can therefore see a claim reduced by roughly the same proportion, even when the loss itself is modest. That mechanism, not the total loss scenario, is what makes an accurate schedule pay for itself.
Plant, fleets and contents
The same discipline applies beyond buildings. Machinery is valued on replacement with a modern equivalent, including freight, installation, commissioning and, where relevant, the cost of downtime and temporary hire. Fleets are scheduled by unit, with specification and specialist bodywork identified. Contents, stock and tenant improvements are frequently the largest omission on a UAE commercial policy.
How often to revisit
Construction cost inflation, currency movement on imported materials and regulatory change all move reinstatement cost independently of the market. A full reassessment every three years, with indexation applied at each renewal in between, is a reasonable discipline for most portfolios — sooner after any material alteration, extension or change of use.
What we deliver
A reinstatement cost assessment sets out the sum insured by asset, the basis on which each figure was built, the assumptions applied, and the rebuild period assumed. Insurers, brokers and loss adjusters work from it directly; at claim stage it is also the document that demonstrates the sum insured was set on a professional basis.
Insurance activity in the UAE is regulated by the Central Bank of the UAE, and policy wordings differ materially between insurers. Read the average condition and the basis of settlement in your own policy — they determine what the sum insured has to achieve.